Project Description
Sloan Security Group provided & installed 7,300 LF of 8FT Welded Wire Fence with barbed wire, and razor wire 5,300 LF of 10FT Welded Wire Fence, with barbed wire and razor wire, 2- manual swing gates,4- operated crash gates, 3 - operated slide gates, 3- wedge barriers, 4- operated swing gates, 49-removable bollards,4 semi automatic bollards, 46-fixed bollards.
Project Challenges
Sloan Security Group was selected to work on the Oroville Dam to improve perimeter security to meet California Department Of Water Resources security requirements, while they were rebuilding the spillway. This project was to protect critical infrastructure from any acts of vandalism or terrorism.
Industry
Dams
Client
Ames Construction
Contractor
N/A