Project Title Pope AFB Security Improvements
Project Location Fort Bragg NC
Project Type Crashed rated barriers, Gates, and Access Controls
Project Description
Provide and Install K-12 Active Vehicle Barrier, K-12 Ameristar 45′ operated double cantilever sliding gate, and communications with Pope AFB existing access controls.
Project Challenges
  • Extremely critical timetable for construction schedule to be completed.
  • Mobilization of personnel and equipment over 2000 miles from Boise.
  • Coordinating with onsite contractors working in very limited space.
  • Unpredictable weather activity resulting in flash floods.
  • Difficult access to project site with numerous security checkpoints.
Client  United States Corp of Engineers
Contractor  ATLANTIC Marine Construction